Application of concrete highway - Couvin (B)

Client:                              BAM Contractors
Implementation period:  2016-2018

The work involved the application of two 8.6 km double lane concrete highways, including emergency lanes and ramps east of Couvin in Belgium. The highway is part of the E420, the main connection between Charleroi and the French border.

Various structural works, including 190,000 m² of concrete hardenings, have been realised. The concrete hardenings consist of double-layer continuous reinforced concrete. The work of phase 1 was completed in late 2016, phase 2 in April 2017, and phase 3 will be completed in 2018.